[Required]
(1) the construction and installation engineering and municipal infrastructure engineering completion approval record table (built by table 1-1-1-3) (retained the original);
(2) engineering completion approval report (construction of table 7-1-7-6) (retained the original);
(3) construction quality and construction units (completed) (building table 5-1-5-3) (retained the original);
(4) the investigation unit project quality inspection report (certificate) (build 3) (retained the original);
(5) design engineering quality inspection report (certificate) (building 4) (retained the original);
(6) supervision and acceptance of construction engineering evaluation report (construction work) (building table 6-1-6-5) (retained the original);
(7) land planning permits, planning permit for construction project (a copy of the identification of original retained);
(8) construction projects construction drawing design document review record book (a copy of the identification of original retained);
(9) Public Security Bureau building fire design review submissions (identification of original retained copy);
(10) the architectural engineering construction license (photocopy of the identification of original retained);
(11) construction project completion planning acceptance certificate (a copy of the identification of original retained);
(12) Public Security Bureau building fire acceptance submissions (identification of original retained copy);
(13) building project monitoring reports on the State of the environment (EIA approval) (copy of the identification of original retained);
(14) building indoor environmental contamination inspection report (civil) (copy of the identification of original retained);
(15) the construction units and construction units signed House architectural engineering quality warranty books (the identification of an original copy is retained);
(16) the residence of the residential warranty on (check original retained copy);
(17) the residence of the residential quality manual "(a copy of the identification of original retained);
(18) lightning detection certificate (a copy of the identification of original retained);
(19) the archives of qualified proof (copy of the identification of original retained);
(20) civilization construction fee payment proof (copy of the identification of original retained);
(21) construction engineering quality supervision station sign inlay returns (fifth and sixth) (retained the original);
(22) work statement (a copy of the identification of original retained);
(23) the third-party settlement observation records (identification of the original copy is retained);
(24) Elevator inspection certificate, crane and other special equipment inspection certificate (a copy of the identification of original retained);
(25) project quality accident, identification and processing report (a copy of the identification of original retained);