The tender documents, contracts and supplementary agreements, construction drawings, construction plans and budget book, completion of plan, statement, design changes, the field of visas, covert works acceptance records, meeting minutes, and the owner with good material price, product information, test reports, etc.
The above information shall be coherent units signed originals.
Project completion settlement information requirements
First, the final settlement information requirements: completion material completion should be documented for complete information, and settlement information submitted after the no exceptional circumstances shall supplement; construction units on the settlement information authenticity, integrity and availability should make a written commitment and responsibility.
Second, the material completion settlement information submissions: provides a complete settlement information two sets (where the application contains three sets of settlement).
Third, the final settlement information:
1 and annex, construction contract and agreement
2. supplementary agreement (if any)
3. notification of winning (selected)
4, construction enterprises calculate standard fees
5. construction project safety evaluation scores and civilized construction fee rate approved table measures
6. Summary of Checkup (signed procedures are complete and clear)
7, open, completion of report and duration extension contact single (signatures of sealing procedures are complete and clear)
8. acceptance record (signed procedures are complete and clear)
9. the tender documents and tender quantities and Flash disk, tender FAQ addendum to the minutes, tender
10, tender documents and e-business standard
11, the tender file technology sign
12, statement prepared by the contractor and the electronic spare (cover the contractor's seal and cost staff qualifications, and signed by the construction units agreed to review, a total of three sets)
13, geological exploration report
14, construction drawings and electronic disk (the copy of the technical drawing diagrams of folding method GB/10609.3-89 uniform collapse into A4 297mm×210mm)
15, the contractor, the Contracting Party, by the supervising Party approved completion drawings (in accordance with the technical drawings to copy figure of folding method GB/10609.3-89 uniform collapse into A4 297mm×210mm)
16, validated construction organization plan, scheme or special construction plan (complete and clearly signed)
17, copied the original terrain elevation measurement records
18, materials and equipment acceptance of nuclear price list (requires a continuous number, signed with complete and clear)
19, design changes, technology approved single (needs a continuous number, signed procedures are complete and clear, complete)
20, site visa single (needs a continuous number, signed with complete and clear procedures, annex complete)
21, for materials (equipment) and accepting the goods receipt
22, concealed works acceptance record (signed procedures are complete and clear)
23, lifting engineering records, installation engineering debug logging, debugging report (signed procedures are complete and clear)
24, and settled the "contracting party notice, directive, meeting minutes, correspondence, project negotiation records"
25. construction units payment (report of progress payment audit report cover)
26. each section, the various professional construction units involve cross-range confirm file of construction
27, settlement, information submitted to the letter of commitment
28. other relevant impact engineering cost, duration and other information
29, transfer of information on sign-off sheet (three copies)
IV. information on composing a binding request:
1. filing requirements: article 3 1-8 in the binding for a volume, 9, 10, 11 and 12 are binding for a volume, 13-14 binding to a volume, 15 and 16 are binding for a volume, 17-21 stapled to a volume, 22-27 items bound to a volume, the 29-page. Based on how much information to the appropriate number or volume.
2, binding requirements: all test paper glue should be left, using the A4 and in the case file inside the directory, the first volume with a volume master directory.
5. other requirements:
1. electronic document statement should have the professional software format and the Excel format, drawings to CAD format.
2. each statement prepared in two parts: first part is to be based on the as-built drawings produced parts, including Checkup records, design changes, technical engineer approved orders, or instructions, constructer construction; the second part of the field of visas, work with records and other relevant costs based on section. New group price list pricing project must provide unit price analysis table.
3 and as-built drawings must have a construction units completed special seal and its related graphs have been signed. By contract, design, supervision and other units confirmed Checkup records, design changes, technology approved single, project engineer with a record, or letting people such as construction directives should be reflected in the corresponding completion chart. On completion of the figure is not reflected in Checkup records, design changes, and works with records, their costs in the settlement is letting people have the right to not be considered.
4. design changes, technology approved single, Visa-, material (equipment) admission price alone, and so share construction, installation professional finishing binding.
5. acceptance of receipt for material receipt on construction units, material suppliers, supervision units, letting people representative's signature and seal of the unit.
6. information for review, for the copy part of the infrastructure management sector construction unit should be sealedAs a basis for strengthening the effectiveness of information.
7. statement of electronic document should have professional software format and the Excel format, drawings to CAD format