How to quickly calculate quantities?

(A) see Figure

Budgeting in front of the picture and the Organization of construction or drawings from the Tribunal, triage of look different. Its methods are:

(1) amending the drawings

First press the checkup records of content and design modifications to cscn content, revised complete set construction drawing. Construction drawing of amendments go ahead, you can avoid later changed drawings, and change has thousands of engineering calculation data, a lot of duplication.

(2) a cursory look at the pictures

This figure also known as "Browse method" set of drawings, in order to achieve the following objectives:

A, understand the basics of engineering. If the building's floors, height, depth, structure based on and around the construction area, etc.

B, the general understanding of engineering materials and practices. If the building ground floor is the cement mortar or terrazzo, outside the walls is water brush stone or dry-stone, the roof is flexible waterproof or rigid waterproof, doors and Windows are made of steel or wood, and so on.

C, understand diagram have a "light table", and "AutoCAD". If so, you want a detailed construction plans, check for errors. Upon verification, in calculating the amount of the corresponding project directly.

D, understand construction drawings representation. Design, construction drawing of representation often some discrepancies. Such as decorative plastering work is in the "decorative table" lists or on the corresponding drawings represent. For some simple project, sometimes you can save a rough look at the picture this step, just take a look at three major figure "architecture" (building floor plans, elevations and sections) you can proceed to calculate the amount of engineering.

(3) see Figure

This is a rough look at the picture above on the basis of more focused, reading the chart. See drawings, mainly construction

"Three figure" and "design description". See the concrete sub-item project calculation "know" when, as a precautionary measure. Also convenient for reasonable, rapidly dividing partial evaluation scope and content.

Use a rough look at the pictures and focus of the picture, you can greatly reduce the time to look at the picture. General engineering drawings, just a few hours to half day for up to one day.

Budgeting in front of the picture, it is not necessary from the point of view of the construction. If the widget installation is appropriate, size and is equal to the total size, construction operations and the difficulties that believe Checkup has been resolved. This figure means purely from the perspective of the budget, in order to exclude the budgeting process barriers. Some people in the calculation of the amount of budget project practice, like the scene construction personnel, spend a lot of effort and a very long time to look at the pictures, it is not necessary. Also some people in the budget for the project calculation does not look at the pictures before, she began with figure, this practice is bound in engineering calculation process, ready to go and read the relevant drawings, result in confusion, reduce productivity, and prone to errors, so it is not desirable.