A perfect engineering design plan must be complete project implementation plan, the two are complementary. Only in strict accordance with the project design and project implementation plans for construction, can guarantee the quality of the project, creating the perfect intelligent environment.
Division of engineering subtasks
1. project management
The main objective of the task is to establish project communication, reporting, and other day-to-day system, which consists of our project managers are responsible for. Mainly includes the following subtasks.
Project plan development
A) with your company to the Project Director and other relevant parties to review and identify the project.
B) development of specific project implementation plan.
C) to develop project progress report format
Progress control and feedback
A) tracking, assessment of project progress.
B in consultation with the responsible party) may appear in the project change.
Submitted to the party a c) weekly.
D) undertake to engineering change management.
E) analysis and auditing engineering change request.
This task only when the project was completed at the end of the round.
2, design engineering programme
This task includes the following subtasks:
Understanding user requirements
Detail design engineering of the various components of the selection, and configuration
Design project implementation programme
This task only when the final engineering design to get the user to confirm before completing.
3, engineering installation: as described in the materials and engineering quote.
This task only when all equipment and materials has been properly installed when completed.
4, label: the main objective of the task to system with eye-catching, easy-to-tag for easy future maintenance, testing connectivity for each subsystem.
This task includes the following subtasks: printing, sticker
5, preparing the acceptance test plan and acceptance: the program's main goal is to develop confirm acceptance testing procedures, processes and standards, and to complete the acceptance.
This task includes the following subtasks:
Determine acceptance project
Determine the acceptance of projects should achieve the functions and indicators
The acceptance plan submitted to the party a
Complete the inspection project
This task only when all the acceptance of the project plan approved by the party, and normal when you have finished all acceptance of projects to complete.
Project progress control, change management
* Modify request
Engineering modifications can be any one of the parties on both sides. Modify the requester must fill out the engineering change request form. By party a specified audit team responsible for the assessment of the proposed modifications. If the audit team agrees to modify to immediately inform us in writing. Otherwise, the audit team should explain to modify the requester. * Modify the response
We received audited Group approved change request within 5 days of a written explanation should be provided to the party a to provide explicitly modify request received and make the appropriate changes and possible additional costs. Party a party b in accordance with our written instructions to reconsider whether or not modified, and inform us in writing of the decision. We provide a decision modifying the programme may include the following:
· File correction table: according to modify request should modify the original file
· Design: according to modify the design of the new
· Testing: according to modify the new test acceptance project
· Performance: according to modify to change the system's performance
· Material: according to modify the material change occurs
· Resource: a resource under modify change
· Duration: according to modify change entire duration, shipping cycles
· Costs: according to modify all materials occurs changes
× Programme audit
We are committed to modify the programme should be approved in writing by the owner before execution.
× Implementation
When written approval from the owner, we should first amendment-related files (including contract, drawings, duration, etc. change entertained, and marked a change of modify the request number, and then modify the programme implementation.
× Project modify process
· By both any party to modify request
· Submits requests to modify the request the audit
· In cases a written confirmation and submit preliminary programme
· The audit team assessed through/veto programme
· Party a written notice through the preliminary programme
· Contractor system "detailed programme"
· The audit team assessed and added reference views
· Party a written notice to the implementation of the programme
· The contractor only if the party a written notice.