【 Weak current College 】 acceptance fine decoration room 14 of the most critical step in
Deluxe Room advantage fine decoration maximum advantage of buying a new house owners, no longer an offering for complicated decoration. Fine decoration needs to bulk purchase building materials, thus saving costs, services are more specialized.
Issues that may arise
Now most of the fine decoration according to the developers and purchasers of the contract is complete, but there are some for profit-driven developers, material suppliers, engineering units of misappropriation of money, use of fake and shoddy construction materials, construction technology, too.
Deluxe room for acceptance
Quality approval is a complex problem, the following are some of your own inspection room is simple to do this:
1. the roof height: with a ruler in the roof to take 4-5 numerical measurement, if agreed, the roof does not tilt.
2. the wall surface: with a long ruler and so close to the wall surface, check whether the flat walls, observation for scratches, cracks in walls for burglary.
3. LaTeX quality: in the surrounding light and dark, high power light bulb (200 watts) radiation, light bright, wall ceiling is formed will immediately seen by the shadow of the light, if uneven, you want to back up PuTTY paint; if local brushed (patched) and wall color variance.
4. door of quality: using a mirror to the top and bottom of door doors, check these usually don't see would ever paint brush. Especially the bathroom door, if the top and bottom of the paint not brush whole, over time, will make the door bottom premature decay damage. Check the security doors have no scratches, deformation, the door if the door is tightly sealed boxes, door and lock switch is flexible.
5. Windows: sliding window on the window and window sash, should feel to promote flexibility, mutual collision-free. The window frame, there should be proof CAP to prevent blocked drain effect.
6. door sealing: check the doors and Windows of the seal is good, may use a long note in the seal point, close enough to slip over exertion, reveals several test seal pressure is uniform.
7. inspection of electricity: owners can purchase a professional electroscope, follow the instructions for use and acceptance by one.
8. empty drum: an exclusive spin (10g) pad percussion on several layers of paper, check the wall walls hollow.
9. check the pipe installation, smooth and sealing: hand hard rock water heater and should be fixed on a solid. If loose, should be fixed. Open water valve see drainage is smooth on the water with tissue paper wipe-down pipe at the bottom of the leakage.
10. radiator: there should be A: radiator vent above, should tweak will drain gas. If the screw is not moving, it needs to be repaired, or the gas exhaust, radiator not hot. B: also note radiator installation fles and return pipe slope to comply with the requirements of, or otherwise affect the heating.
11. kitchen flue: paper volume after fire ignition, placed in tobacco smoke level crossing below 10 cm or so to see whether the smoke rose to smoke level crossing turn sucked away immediately.
12. pipeline gas used the smoke of paper near the alarm device, see the device is sensitive; alarm sound and light tips at the same time closes the inlet solenoid valve, and if not, to timely repair.
13. bathroom: A toilet in loudaonei window should install burglar mesh. B: If no window, you should have the ventilation holes. Ventilation holes are located in the ceiling. From the nearest outlet vents shall be waterproof socket.
14. the kitchen and bathroom: these two places are ceramic tiles to the top, to check the corners without kepeng (four corners of the roof and floor), and floor tiles wall deformation and cracking and empty drum. Use an designated hammer floor tiles and wall tiles, empty sound, should be laid.