【 Weak current college 】 budget experience (17)


For these reasons, the tenderer to tender documents, according to the requirements of bidding documents, to control drawings, control of tender documents is available on a review of quantities or composite. The tenderer to review projects? here are through years of experience, make a few suggestions for your reference.

First, to find professionals in specialized on construction plot of quantitative review.

At present in many of the tender process, the first time, the general public tender only one week review of the project; the second is the tenderer the majority believe that there are no quantities is tender units, but it is not, if the tender documents required tenderers review of quantities, you have no review, inventories, tender units themselves, otherwise, to the tenderer to clarify what time? third tenderer would not of money looking for more professional construction plot of quantity examination, perhaps think of money from the big role; the fourth is divided into professional review, because the project cost is a large comprehensive professional development in specific quantities, according to the drawings of professional structure of the building and, electrical equipment and lighting, drainage and fire water system, air conditioner, power engineering (integrated distribution, broadcasting systems, fire alarm systems, security systems, etc.), these professionals have their own norms, standards, not just simple drawings on the length of the pipeline. So demanding professional on construction plot of quantitative review.

Second, according to the description and drawings of various selection criterion on the contents of the list.

This is for preparation of BOQ for professional level and requirements. If the professional requirements for scaffolding, building works has its method of calculation and installation engineering, electrical and plumbing works is not the same. And if the installation works, many of the electrical equipment commissioning work (Busbar system debugging and debugging low voltage power supply system, etc), I come into contact with tender quantities, often overlooked this expense is the construction company will never done the work, or do they never received the costs, I have no idea. But I want to affirm that to the tenderer, the do you want to do, it's also going to take, to get comfortable, get reasonable. Not the holding does not know how, they also feel that the deficit, it had to do in other areas, do not offer. Although the quote, the price of similar but different content, shouldn't want you to. In addition, sometimes the list though, like electrical tubing pipe, pipe DN32---70m laying of the way there is no description, or there are two ways downlead, concealed, by now, you had to note from the drawings to identify the laying or separation under the drawings of the project in two ways, such as the downlead 50m 20m, concealed. And if in a septic tank for water supply and drainage, sometimes according to the drawings of the instructions and find standard Atlas can set fixed.

Third, according to the technical requirements and the specific requirements of the tender documents, on the need to increase the content of the review.

Front repeatedly emphasized the tender documents, careful study of tender documents is how we fight for the successful tenderer, the first thing to do. In the past, I am often asked, how to achieve successful qualification, my method is the first serious study of tender documents, although the tender documents is basically the same, but each project has its own special requirements, these requirements will be reflected on the tender documents, except that many bidders that are the same, no look. Some works of quantities of content on demand increases and technology requirements or the requirements of bidding documents, through the review and clarify this.

4. for a fixed price contract, to projects subsidiary engineering, easy to change the content of the review.

For quantities plus fixed price contract, paying particular attention to the careful review ancillary works. Because there is a subsidiary of the project, you cannot simply rely on subjective awareness, want to visit, it may happen to be comprehensive, get a competitive quote. Due to bidding strategies, to easily change the content of the specific analysis, viable price.

5. Organization of the new specification to seriously study the cost of personnel, careful study.

In new construction projects resilience detailed list counts the price code, add the action item list. It refers to the completion of the project construction must take the necessary measures. The content must be combined with project construction organization plan or construction organization plan of the case may be, therefore, review, always according to its own construction project or construction organization plan be amended.

In addition to make the point that if bidding documents on quantities are annotated, not modify its quantity, bid strategy is based on the quoted price, do add that that is the quantities is wrong place, so that not only makes your bidding in line with the actual project and make your offer more competitive, to judges and owners a complete project quote.

In summary, a review of the methodologies of quantities, for a experienced cost engineer, he must have its own set of review methods, here, just start, some experiences for counterparts.