Saturday, December 18, 2010
【 Weak current College 】 latest "architectural engineering construction area calculation norms
People's Republic of China Ministry of construction
Table of contents
1 General provisions
2 terminology
3 calculate the area of
This specification uses the term description
Provisions description
1 General provisions
1.0.1 is a specification for industrial and civil construction engineering area calculation, uniform calculation method, the development of this specification.
1.0.2 this specification apply to new, expanded and reconstructed for industry and civil construction engineering area.
1.0.3 building area calculation should follow the principles of scientific and reasonable.
In addition to the architectural area calculation 1.0.4 should follow this standard, there should be consistent with national standards of existing relevant norms.
2 terminology
2.0.1-storey storyheight
Upper and lower floor or floor and vertical distance between the ground.
2.0.2 natural layer floor
According to the floor, stratified floor floor structure.
2.0.3 emptyspace overhead layer
Building on deep foundations or suspending the aerial parts of building not backfill Earth forms the architectural space.
2.0.4 corridor corridorgo11ory
The building level of traffic.
2.0.5 pick Gallery overhangingcorridor
Pick the level of traffic on the external walls of buildings.
2.0.6 eaves eavesgo11ory
Set out in building the underlying level traffic under the eaves.
2.0.7 cloisters cloister
In building hallway, Hall is set in the second floor or second floor above back-shaped corridor.
2.0.8 door foyer scoop
At the entrances and exits of buildings up to separate, wind, cold, etc. of building transitional space.
2.0.9 building corridor passage
The road passes through the building of architectural space.
2.0.10 aerial corridor bridgeway
Buildings and structures, between the second floor or second floor above the level of traffic set specifically designed for the corridors.
2.0.11 Le feet plinth
The external walls of buildings and the outdoor ground or bulk water press contact parts of walls thicken.
2.0.12 envelope envelopenclosure
Combined with the architectural space surrounding walls, doors, Windows, etc.
2.0.13 enclosure of curtain wall enclosingcurtainwall
Directly as the role of external wall up the exterior curtain wall.
2.0.14 decorative curtain wall decorativefacedcurtainwall
Set in a building wall in vitro decorative curtain wall.
2.0.15 landing shopwindow Frenchwindow
Highlight the outside wall Foundation landing window.
2.0.16 Terrace balcony
For users to carry out activities and drying clothing of building space.
Look-viewroom 2.0.17
Set in the building top floor or single out room for people to view or observation of surrounding circumstances of the architectural space.
2.0.18 awning canopy
Settings in the upper part of the building and export rain, awning.
2.0.19 basement basement
Rooms at ground level is lower than the height of the exterior of the plane than the room height measured in 1/2 of a basement.
Semi-basement semibasement 2.0.20
Rooms at ground level is lower than the height of the exterior of the plane than the room height measured in 1/3 and no more than 1/2-half basement.
Deformation joint deforrnationjoint 2.0.21
Expansion joints (temperature joints), settlement joint and seismic gap.
Permanent cover permanentcap 2.0.22
The planning approval design of permanent use of the top cover.
Baywindow 2.0.23 floating window
As room lighting and beautify the appearance and settings of the external walls of the window.
2.0.24 arcade overhang
Floor portion of the sidewalk across the street building.
2.0.25 guojielou arcade
A road runs through the architectural space of the building.
3 calculate the area of
3.0.1 the construction area of single-storey, its exterior Le feet above the level of area around the structure, and should meet the following requirements:
L-storey height in 2.20m and above should calculate the height of the whole area; insufficient 2.20m '1/2 should be counted.
2 use of sloping roof space is assumed to exceed 2.10m parts should be calculated in the total area: clear height to 2.10m parts 1.20m should juice counts as 1/2 size; insufficient l.20m part height should not be computing area.
3.0.2-storey houses local floor, second floor of the local Club level and above the floor, with the support structure should be the level of its envelope peripheral space, no envelope should its structure and floor level area calculation. Storey in 2.20m and above all, should be calculated; layer high enough 2.20m should calculate 1/2 area.
3.0.3 multi-storey buildings first layer should be above its exterior Le foot level in the area surrounding the structure; the second layer and above the floor should be the external wall structure peripheral level area calculation. Storey in 2.20m and above shall be the whole area; juice layer high enough 2.20m should calculate 1/2 area.
3.0.4 multi-story building sloping roof and venues stands, when design utilized when applying over 2.10m parts should be calculated in the total area; clear height to 2.10m parts 1.20m should calculate 1/2 area; when the design does not use or indoor height should not be less than 1.20m area calculation.
3.0.5 basements, half basement (shop, shops, station, garage, warehouse, etc.), including the permanent cover entrances should be exterior wall outlet (not including the lighting well, dampproof coating and protection walls) outside the area surrounding horizontal line. Layer high above the 2.20m and should calculate the total area; storey insufficient 2.20m should calculate l/2 area.
3.0.6 hillside building crane feet overhead, deep Foundation overhead layers, design utilized and envelopes, storey in 2.20m and above all the parts should be calculated; storey insufficient 2.20m part 1/2 should be counted. Design utilized, no envelope of architectural metal feet overhead layer should be use parts of the level of the area of l/2; design does not take advantage of the deep underlying aerial layer, sloping suspension foot aerial layer, multi-layer architecture sloping roof, the stadium stands of space should not be computing area.
3.0.7 building hallway, Hall by a tier computing area. Hallway, Hall is equipped with a cloister, should its structure and floor level area calculation. Layer high above the 2.20rn and should calculate the total area; storey insufficient 2.20m should calculate 1/2 area.
3.0.8 buildings between the elevated corridor of envelope, the envelope peripheral level area calculation. Layer high above the 2.20m and should calculate the total area; storey insufficient 2.20m should calculate 1/2 area. There is no permanent roof should be of the enclosing structure according to their structure and floor level area of l/2.
3.0.9 stereo library, warehouse, parking, non-structural layer should be calculated on a layer, the layer should its structure layer area calculation. Layer high above the 2.20m and should calculate the total area; storey insufficient 2.20m should calculate l/2 area.
3.0.10 has the envelope's stage lighting control room, you should press the envelope peripheral level area calculation. Layer high above the 2.20m and should calculate the total area; storey insufficient 2.20m should calculate 1/2 area.
3.0.11 buildings outside the envelope's landing window, door and pick Gallery, corridor, eaves, should press the envelope peripheral level area calculation. Layer high above the 2.20m and should calculate the total area; storey insufficient 2.20m should calculate 1/2 area. There is no permanent roof should be of the enclosing structure according to their structure and floor level area of 1/2.
There is no permanent cover 3.0.12 envelope complex stands should be the top level of the projected area of l/2.
3.0.13 building at the top of the envelope's staircase, water tanks, engine room, Elevator, layer high above the 2.20m and should calculate the total area; storey insufficient 2.20m should calculate 1/2 area.
3.0.14 with envelope is not perpendicular to the horizontal plane and beyond the bottom outer edge of the building, its floor surface area calculation for peripheral level. Layer high above the 2.20m and should calculate the total area; storey insufficient 2.20m should calculate 1/2 area.
3.0.15 building interior stairs, elevator shaft, sightseeing elevator shaft, extracts of wells, pipelines, wells, ventilation exhaust shafts, ventilation road, with wall chimney should be natural tier computing building.
3.0.16 awning outside the structure to be outside the exterior wall structure exceeds the width of the line, should press 2.10m awning fabric plate horizontal projection area of 1/2 meter of skip.
3.0.17 have permanent top outdoor staircases, should be the level of the natural layer buildings projected area of 1/2.
3.0.18 buildings balconies are according to their level of projected area of 1/2.
There is no permanent cover 3.0.19 envelope shed, booths, platform, station, toll, etc., should be the top level of the projected area of 1/2.
The high-low with cross-3.0.20 buildings, high cross-structure outside line as a separate calculation area; its high and low across internal connectivity, its deformation seams should be evaluated in a low cross-area.
3.0.21 to curtain wall as the building envelope, curtain wall outside line calculates the construction area.
3.0.22 building exterior side of the insulation layer, insulation layer outside line calculates the construction area.
3.0.23 building deformational slots, should be the natural layer merge in building area.R>
3.0.24 following items should not be calculate area:
1 building channel (arcade, guojielou underlying).
2 the building equipment piping dissection.
3 buildings separated single room, stage and backstage hanging curtains and scenery of the flyover, pick one, and so on. ,
4 roof tanks, flower stand, gazebo, balconies, open-air swimming pool.
5 building operation platform, loading platforms, installation of the tank and the tank's platform.
6-foot, with walls, crib, steps, wall plaster, decorative surfaces, glued on the block layer, decorative curtain wall, air conditioners, machine shelf (carton), floating window, Widget, gadget, width in 2.10m and terminals, as well as within and buildings not connected to the pass of decorative balcony, single gallery.
7 no permanent cover elevated corridor, outdoor stairs and is used for maintenance, fire, and other outdoor steel stairs, climbing the ladder.
Eight escalators, automatic sidewalk.
9 independent chimney, flue, trench, oil (water) tank, gas tank, water tower, oil storage tank, (water) silo, trestle, underground air defense channel, subway tunnels.
This specification uses the term description
1 in order to facilitate the implementation of this specification provisions distinguish between, on the strict wording of the different levels are described below:
1) that is very strict and non-do not use of words:
Positive terms "must", "non-negative terms."
2) indicates that, under normal circumstances should be done with the words:
Positive words use "should", "negative words used and should not be" or "no".
3) that allows a choice in conditions permit first should be done with the words:
Positive words use "should", "should not be used as negative words."
Indicates that a choice, under certain conditions, can do so using the word "may".
2. this standard should be specified in other relevant standard, normative implementation written as "should be consistent with the ... Requirements "or" should be ... Perform ".
Architectural engineering construction area calculation specification provisions description
1 General provisions
The building in China 1.0.1 area calculation rules in the 1970s by the former Soviet Union approach combined with our situation developed by the National Capital Commission in .1982 Office (82) via radicals set Word 58, issued the construction area calculation rules are on the 1970s the construction area calculation rules for amendments. In 1995, the Ministry issued the national unification architectural engineering budget engineering calculation rules (civil engineering GJI) cz-101-95), which included the "building area calculation rules" (hereinafter referred to as "the original area calculation rules"). For the 1982 construction area calculation rules for amendments.
Historically, the building area calculation rules in the construction cost management plays a very important role in the building housing the calculation of quantities of key indicators, is calculated unit project budget cost per square meter of main basis. Is the summary statistical departments publish housing construction area of completion of the Foundation. Currently, the Ministry of construction and national quality technology supervision Bureau issued the real measurement standards "of the real estate area, as well as the residential design specifications" in the area of computing, are based on the building area calculation rules. As China's construction market development, the building of new structures, new materials, new technologies, new construction methods, in order to address the building technology development in the area of computational problems that make a building area of more scientific and rational, improvement and harmonization of building area of computing and computing methods, on the construction market play a bigger role. Therefore, on the building area of calculation rules to be amended. Considering that the construction area calculation rules for the important role that this will be the construction area of calculation rules to the architectural engineering construction area calculation specifications (hereinafter "the code").
The scope of this specification 1.0.2 is a new, expanded and reconstructed for industry and civil construction engineering construction area of computing, including industrial plants, warehouses, public buildings, residential buildings, agricultural production used for housing, grain kind of warehouse, subway station, and a building area of computing.
3 calculate the area of
3.0.1 the specification construction area of computing is to Le feet above outside the exterior wall structures route calculation. Le foot is the wall is part of the root is short wall thickening, cannot represent the entire exterior wall structure, therefore to deduct Le foot thick walls.
3.0.2 storey height should be different to determine its size calculation. Its height means indoors ground elevation to the roof deck structure in the vertical distance between the elevation. Where to find the slope of the roof-flat roof-deck building. Its height means indoors ground elevation to roof panel lowest plate surface structure of the vertical distance between the elevation.
On the sloping roof space how to calculate area, we reference the residential design code of the relevant provisions of the sloping roof height measured according to the different buildings to determine its size calculation. Clear height means the floor or ground comes first at the end of the floor or ceiling vertical distance between the bottom surface.
3.0.3 multi-storey buildings of architectural area calculation should be based on different floors respectively. Storey height refers to the upper and lower floor structure of the vertical distance between the elevation. Building the bottom storey, Foundation Press Foundation slab surface structure on the first floor of the structure of the vertical distance between the elevation; no base means the ground elevation is Supreme floor structure for the vertical distance between the elevation, the highest level of storey is its elevation of floor structure to the roof deck structure in the vertical distance between the elevation where to find the slope of the roof-roof, storey means buildingSurface structure of the roof panel minimum level to the Board structure at the level of the vertical distance between.
3.0.4 multi-story building sloping roof and venues stands under the space should be regarded as a space within the sloping roofs, design utilized, should be assumed to determine their size calculation. Design does not use space, building area should not be evaluated.
3.0.5 basements, half basement walls to its estuary edge the Wai level area calculation. The calculation rule by the basement, semi basement walls perimeter level on the estuary area calculation, not very closely on the text, "the wall" on the estuary is easy to understand for basements, half basement of a building's exterior wall. Due to the exterior and basement walls of the center line is not necessarily fully overlapping, mostly I extrude or recessed basement wall centre line.
3.0.6 built in a building on suspending aerial layer (see Figure 1).
Figure 1 slope construction crane feet overhead layer
The provisions of this section on the original 3.0.9 were revised and increased parking area calculation. Garage, warehouse, three-dimensional stacks does not stipulate whether retaining structure, according to whether there is a structural layers. you should distinguish between the different layers high determine the scope of building area calculation. change according to the shelves and shelves of tier computing area.
This section called the "3.0.12 venue" essentially means "field" (for instance: the football field, tennis courts, etc.) have permanent cover on the stand. The "Museum" is a permanent top and envelopes shall, at the single-layer or multi-layer architecture related requirements calculation area.
In case of building roofs 3.0.13 staircase is the slope of the roof, pitched roof should be according to the relevant provisions in the computing area.
3.0.14 with envelope is not perpendicular to the horizontal plane and beyond the bottom outer edge of the building is a building tilt wall. in case of an inclined to building walls, sloping roof should be considered. According to the relevant provisions of the sloping roof area calculation.
3.0.15 indoor stairway area calculation, you should press the staircase attached buildings the calculation of natural floors and the building area. In case of thermocline architecture, its common indoor stairs should be natural tier computing area: upper and lower error levels Middle air-condition common Interior stairs, candidates with a layer of
Figure 2 Schematic staggered section Middle air-condition
3.0.16 awning with its width exceeding 2.10m or not exceeding balance, more than 2.10m 2.10m users should press the awning fabric plate horizontal projection area calculation of l, 2. The column with column awning and awning calculation should be consistent.
3.0.17 outdoor staircase, at the top of stairs without permanent cover, or cannot fully cover the stairs of the awning. The upper stairs not calculate area, upper staircase can be considered as the lower stairs of permanent cover, lower stairs area should be evaluated.
3.0.18 building terrace, balcony concave balcony, balconies, closed and closed terrace are its horizontal half of the projection area.
3.0.19 shed, booths, platform, station, toll, etc., area calculation. Due to the development of architectural technology, many new structures, such as column no longer simply an upright column, but there are V-shaped pillars,
Inverted ^ column, different types of columns, giving the area a lot of controversy, and we don't to column to determine the area of computing, and the top cover of the horizontal projection area calculation. In the carport, booths, platform, station, toll stations are equipped with a support structure for managing rooms, lounges and other press-related provisions of the PCT area calculation.
3.0.23 this specification refers to building expansion joint is connected with the building of deformation seams, which is exposed in the building, in a building can be seen by the deformation of joints.
3.0.24 other building area should not be evaluated.
6 prominent wall of Le feet, with walls buttress, steps, wall plaster, decorative surfaces, glued on the block layer, decorative curtain wall, conditioners shelf (box), floating window, Widget, gadget, width in 2.10m and within the canopy and buildings not connected to the pass of decorative balcony, pick Gallery are not part of the building structure, building area should not be evaluated.
8 escalator (helical walkway by escalator), apart from both ends of the floor boards or beams, the ladder itself belongs to the device. The calculation for this ladder is not suitable for the construction area. Level trail (escalator) is installed in the floor on the device, it should not be a separate calculation area.
Labels:
[:]