People's Republic of China Construction Ministry published Bulletin No. 536, ratification of the intelligent building design standard "GB/T50314-2007 since July 1, 2007, in place since the original" intelligence architectural design standard "GB/T50314-2000 abolished at the same time. The standards development under the situation of China, on the domestic application of intelligent building a lot of new requirements, including the first 12 chapters for residential buildings, as follows:
12.1 General provisions
12.1.1 this chapter apply to residences, villas and apartment buildings.
12.1.2 intelligent system should meet the following requirements:
1, should reflect the people-oriented, safety, energy efficiency, comfort and convenience.
2, should be consistent with the construction of environmental and health requirements for the green building environment.
3, should be introduced on the standardized management of residential buildings
12.1.3 residential construction intellectualization system's basic configuration should meet the following requirements:
1. to configure Intelligent integrated systems.
2. to configure communication access system.
3, to configure the telephone switching system.
4. to configure information network system.
5, to configure the cabling system.
6, cable television systems should be configured.
7, to configure the public broadcasting system
8, to configure the property information management system.
9, to configure the system for building equipment management.
10, automatic fire alarm system should be consistent with existing national fire safety norms.
11, security and protection system should be consistent with existing national standards for the security and protection engineering specification GB50348.
12.2 residential
12.2.1 household configuration meets the following requirements:
1. configure the home wiring boxes. Home wiring box at the configuration of the phone, television, information networks, and other intelligent systems House line access point.
2, should be in the main bedroom, study room, living room, room configuration information on port.
12.2.2 Residential (district) to configure the water meters, electricity meters, gas meters, heat energy (heating) table automatic metering, copied and remote systems, and Yi and utility management system.
12.2.3 to build residential (district), property management and comprehensive information platform. Realization of property company office automation systems, community information publishing system and vehicle access control system of integrated management. The community should apply smart card system.
12.2.4 security and protection system configuration should not be lower than the national current standards of the security and protection engineering specification GB50348 increase for the configuration of the security system.
12.3 Villa
12.3.1 should configure Intelligent integrated systems.
12.3.2 underground garage, lift, etc should configure indoor mobile communication coverage system.
12.3.3 should configure public service management systems.
12.3.4 to configure smart card application system.
12.3.5 suitable configuration information network security management system.
12.3.6 Villa configuration meets the following requirements:
1. configure the home wiring boxes and home controller.
2, in the bedroom, study room, living room, bathroom, kitchen configuration information on port.
3. configure the water meter, electricity meters, gas meters, heat energy (heating) table automatic metering, copied and remote systems, and Yi and utility management system.
12.3.7 should establish Internet sites and data centers, providing property management, e-commerce, video on demand, on-line information query and service, telemedicine and distance education, and other value-added services.
12.3.8 Villa construction equipment management system should meet the following requirements:
1, should monitor the public lighting system.
2, should monitor the water supply and sewerage system.
3. should the monitoring central air conditioning/heating and cooling equipment status, run make barrier monitoring steam, hot and cold water temperature, flow, pressure and energy consumption, monitoring exhaust air system.
12.3.9 security technology system configuration should not be lower than the national current standards of the security and protection engineering specification GB50348 advanced security system configuration standards and should meet the following requirements:
1. to configure the perimeter of the video surveillance system, the use of perimeter intrusion detection alarm device and perimeter lighting, video surveillance, and have linked external alarm interface.
2, the guest speaker at the door the host can use the smart card or to human characteristics and identifying technology means opening the door.
3, first floor, second floor and the top level window, balcony intruder alarm detector should be located.
4, gas gas pipe to configure the automatic valve, leakage alarm signal automatically close the valve, cut off the gas.
Standards body with integrated wiring directly related to the following provisions: ① should configure home wiring boxes. Home wiring box at the configuration of the phone, television, information networks, and other intelligent systems house cable access points; ② should be in the main bedroom, study room, living room, room configuration information on port. ③ the entire community to configure cabling system.
Standards to regulate the terms used are explained in the following:
⑴ that strict, under normal circumstances should be done with the words: positive terms "should be"; negative terms "should" or "no";
⑵ allows slightly, in conditions of the license, the first thing you should do the same term: positive terms "suitable"; negative terms "unsuitable". Indicates that a choice, under certain conditions, can do so using the word "may". From the standard body and standard wording explaining terms can be seen home wiring isAs for the basic requirements for residential construction, the general sense, all new residential should install home wiring box, each room also should install the port, the entire community of information recommended installation cabling system. Therefore, as the new national standard on July 1, 2007, the official implementation of domestic residential construction in the family home wiring box (multimedia wiring box) will be widely installed, the main room in residence will also require the installation of the entire community information port, recommended installation cabling system. As the national standards authority and seriousness, will greatly promote domestic community intelligence, information technology building, including some previously relatively backward regions. Home wiring products market will usher in a new round of development.