【 Weak current College 】 electrical engineering, intelligent building engineering construction quality overseeing implementation regulation (template) 6
8. this project electrical installation work, intelligent building project overseeing work methods and measures
Construction supervision and control of the quality of the final hurdle. Supervising engineer to adhere to each process is not authorized, will not be allowed to turn into accepting the next procedure. You must read the design drawings, Merton entered the supply scheme and key data for the checkup and design changes alone, please mark the corresponding construction plans.
8.1 Executive certificates system, electrical technology managers, operations staff, should have the appropriate technical titles and effective operation of qualified jobs, and registration. Supervising engineer to master the technical quality and movement, be aware of.
8.2 implement electrical engineering construction, construction management engineer to party reported by various engineering and inspection of single built-in works to construction drawings and specifications and construction craft standard requires careful review. Problems, questions, bug should timely processing, clearly, not left to the next procedure.
8.3 supervising engineer to strictly enforce the rules and regulations, good engineering. Design, technology, materials, equipment changes should handle the negotiation then construction project. The various procedures for documents as proof that the timely fill out log, mastering dynamic construction.
8.4 supervising engineer to check oversight contractors whether sound quality assurance system, the implementation of the three types of inspections (post, mutual seizure, junction detection) system, three press (press drawings, then process, according to the standard) system implementation.
Switch on the power supply system, 8.5 system main equipment installation and debugging, supervising engineer to personally supervise the validation, master the detailed technical information and actual situation. Check if you meet the design requirements and acceptance of request record.
8.6 on construction of new technologies, new equipment, new technology, new methods and maintenance equipment, construction process and must be modified, supervising engineer must reference the original design requirements, audit, and construction units and design units written consent and approval of the relevant business units.
8.7 supervising engineer to regularly attend the regular site, organized according to the needs of the professional coordination meetings, such as processing orders designated item, construction unit direct subcontracting projects and General Contracting units designated item, professional strong subcontractors venue coordination.
8.8 in contracting units quality control personnel post qualified, based on inspection of part of contractors to conduct covert works acceptance. To make timely and full information on the collection of related technologies and inspection records. According to the actual progress and quality, regular fill out schedule, the quality of the project should meet the relevant technical standards, design documents and contract requirements. Do intermediate test and closeout debugging with complete technical archives and completion chart information.
8.9 medicine supply conditions, if necessary, help the construction units to develop appropriate rules and regulations, to run the transmission trial operation at the beginning of the creation of conditions for a smooth transfer to engineering warranty period.
8.10 electrical installation, construction and other professional cooperation and coordination of construction, construction management engineer should always supervise the entire process, check, coordination with other professional electrical engineering with the Division of responsibilities between clear, acceleration, and ensure project quality, reduce consumption.
8.10.1 Foundation construction phase, supervise construction professional construction personnel indicated by civil figure through the Foundation's pipeline location reserved hole, electrical professionals meet the civil construction, reserved for civil construction diagrams should be indicated and reserve hole into the Foundation layer of pipelines, grounding device.
8.10.2 structure construction phase, supervise electrical professionals and civil construction professionals closely, on lightning protection facilities and cited the following line to the margin of ground 1.8m Department leads to chain a checkpoint, each three-layer sets a pressure zone, shall be prepared in advance of embedded parts, civil construction in place when embedded in a timely manner.
8.10.3 plastering phase:
(1) supervision and inspection of electrical engineering of the carton, box, pipes, casing is completely intact, unqualified timely remedial, repair.
(2) wallpaper or spray before check box, box, card and reserve hole location and size, find missing timely remedies.
(3) electrical engineering pipeline, power distribution box, bearing the face should be installed, such as the wall uneven or chips, shall promptly remedy.
(4) box, box port to the rules and flat, not allowed to stay big horn that, consistent with the wall.
(5) electrical construction personnel must box, box sealing (with paper or other material) protection box, preventing pollution, fell into foreign objects.
8.10.4 shotcrete and its later stages:
(1) to supervise the shotcrete personnel protection junction box, switch boxes, socket, box, carton, box.
(2) spray after the lighting equipment and panel installation, action stations right, civil protection, prevention of walls of finished products
Dirty chipped.
8.10.5 electrical construction and civil engineering complexes should be in the possession of the lines:
(1) axes, axis calculated tube, lines, boxes, boxes of plane location and relationships.
(2) underwater cables, typically 50 lines or 1M lines, electrical appliances in this location.
(3) the wall line, before construction-reinforced plaster to determine the wall, should be the standard for electrical construction, adjustment of the various boxes and boxes of location.
(4) under the skin line, ceiling decoration, the ceiling is adjusted under the skin lines installed embedded lamps and pull cord switch terminal box position of benchmark.
(5) partition wall and door centerline, as according to determine the position of the lamp, switch.
9. electrical installation engineering, intelligent building engineering acceptance should submit information file
9.1 motor
9.1.1 change design part of actual construction drawings;
9.1.2 changesDesign of supporting documents;
9.1.3 manufacturers provide product specifications, test records, certification and installation drawings and other technical documents;
9.1.4 installation technical records (including motor pulling inspection records, the electrical drying records, etc.);
9.1.5 adjustment test records;
9.2 power strips, complete sets of Cabinet and secondary circuit wiring
9.2.1 change design part of actual construction drawings;
9.2.2 change design of supporting documents;
9.2.3 manufacturers provide product specifications, test records, certification and installation drawings and other technical documents;
9.2.4 installation technical records;
9.2.5 adjustment test records.
9.3 battery
9.3.1 manufacturers provide products manual, certificate and related technical documents;
9.3.2 installation technical records (charging or discharging records and curves, etc.);
9.3.3 material inspection report.
9.4 low-voltage electric apparatus
9.4.1 change design part of actual construction drawings;
9.4.2 change design of supporting documents;
9.4.3 manufacturers provide product specifications, test records, certification and installation drawings and other technical documents;
9.4.4 insulation resistance and voltage test records;
9.4.5 adjusted, setting of low voltage electrical adjustment records.
9.5 wiring works
9.5.1 change design of supporting documents;
9.5.2 alterations design part of actual construction drawings;
9.5.3 installation technical records (including concealed work records);
9.5.4 test record (including insulation resistance test records).
9.6 electric lighting
9.6.1 change design of supporting documents;
9.6.2 manufacturers provide product specifications, test records, certification and installation drawings and other technical documents;
9.6.3 change design part of actual construction drawings;
9.6.4 installation technical records (including concealed work records);
9.6.5 test record (including lifting large lamps overload test records).
9.7 earthing device
9.7.1 change design part of actual construction drawings;
9.7.2 change design of supporting documents;
9.7.3 installation technical records (including concealed work records);
9.7.4 test record (including grounding resistance test records).
9.8 intelligent building engineering
9.8.1 the quality of equipment and materials;
9.8.2 implicit check (with workers check) acceptance record;
9.8.3 change auditing, design changes, with a record;
9.8.4 engineering installation quality and perception of quality acceptance record;
9.8.5 system records;
9.8.6 system test records;
9.8.7 subsystem test records;
9.8.8 enforcement provisions test records;
9.8.9 system (partial engineering) detection summary record;
9.8.10 Division (Sub Division) engineering completion approval records.
9.9 other