Wednesday, January 26, 2011
【 Weak current College 】 newly installed elevators acceptance inspection application procedures
I. the inspection basis
According to the special equipment safety supervision Ordinance 21: boiler, pressure vessel and pressure piping components, lifting equipment, the large amusement facilities manufacturing process and boiler, pressure vessel, elevators, cranes, passenger ropeway, large-scale amusement facilities, installation, renovation, major maintenance procedure, must be approved by the State Department special equipment Security Administration approval testing and inspection bodies in accordance with the security specifications for supervision and inspection; without the supervision of qualified delivery shall be ex factory or. Second, examination standard
1, elevator control and inspection procedures;
2, the elevator installation inspection specifications (GB10060-1993);
3, the elevator manufacturing and installation of the security code (GB7588-1995);
4, the escalators and passenger conveyors of the Statute of the monitoring and inspection;
5, the escalators and passenger conveyors of the manufacturing and installation of the security code (GB16899-1997);
6, the rules for the inspection of modifications supervision;
7, the service lift (JG135-2000);
8, the hydraulic elevator control and inspection procedures;
9, the hydraulic elevator (JG5071-1996). III. application for inspection
Hold the following information to the application:
1, use the elevator inspection units complete the application form (required to cover the use of flat seal);
2. inspection fees payment voucher;
3, inform the Attorney, told the book receipt;
4, machine certificate;
5. packing slips;
6, the sales contract;
7, post address and post record;
8, try running records;
9, concealed construction of record;
10, if you have changed the original construction programme, there should be a change in the construction of record.
Such as the use of units of application materials is incomplete or does not comply with the statutory form, on the spot or in 5 days time inform the applicant of the required correction. To complement the information to the applicant, giving the admissibility and arrange for the appropriate test. IV. service acceptance
In accepting applications, 10 working days of the scheduled inspection, quality and technology supervision given to the scene of an administrative decision on the application inadmissible. 5. implementation of the field-conditions
1, elevator for post, do a self test reports;
2. ready rated load of 125% of the standard test weights;
3. prepare the relevant files, System (Elevator electrical schematics, Elevator administrator actions card, etc.) for future reference;
4. elevator use, installation units should arrange relevant professional personnel to the scene with inspection. 6. test report to produce and disseminate
Inspection is completed, within 10 business days to produce the "elevator inspection report". Probably this is the case, specific or where do you want to see!
No comments:
Post a Comment